Justia South Carolina Supreme Court Opinion Summaries

Articles Posted in Contracts
by
The respondents, two developers and an architectural firm, Stevens & Wilkinson of South Carolina, Inc. (S&W), entered into a Memorandum of Understanding (MOU) with the City of Columbia as part of a larger project team to develop a publicly-funded hotel for the Columbia Metropolitan Convention Center. The City eventually abandoned its plan under the MOU, and the respondents brought suit on several causes of action including breach of contract and equitable relief. The City moved for summary judgment arguing the MOU was not a contract and therefore the contract claims failed. The circuit court agreed and, rejecting the equitable claims as well, granted summary judgment in favor of the City. The respondents appealed and the court of appeals affirmed in part and reversed in part. The Supreme Court reversed. Because the MOU was comprised of agreements to execute further agreements, there was no meeting of the minds on numerous material terms which had not yet been defined. Accordingly, the court of appeals was reversed with respect to that portion of the court's judgment; the Supreme Court held the MOU was unenforceable as a matter of law. The Supreme Court agreed with the circuit court and reinstated its judgment in favor of the City. View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law

by
In April 2003, the City of Columbia entered into a Memorandum of Understanding (MOU) with Stevens & Wilkinson of South Carolina, Inc. (S&W) and several other parties, to develop a publicly-funded hotel adjacent to the Columbia Metropolitan Convention Center. As architect, S&W was to complete sufficient preliminary design work to determine a guaranteed maximum price for the project, which would be used by the City to obtain municipal bond funding to cover the cost of the hotel. Pursuant to the MOU, the construction company was to pay S&W directly. On June 26, 2003, the City received a letter stating S&W would complete its preliminary design on July 10, 2003, and would then stop working until the bond financing for the hotel was finalized. Realizing this could delay the start of construction, S&W offered to continue working the remaining ninety days until the anticipated bond closing date of October 13, 2003, but required assurance it would be compensated for the work it performed during this time frame. It provided an estimate requiring $650,000 and $75,000 per week after that. On July 30, the City approved "$650,000 for interim architectural design services for a period of 90 days prior to bond closing." The bond closing did not occur as scheduled, but S&W nevertheless continued to work. S&W submitted an invoice to the City for $697,084.79 for work that took place from July 10 to December 15, 2003. By letter dated December 17, 2003, S&W informed the construction company that the City had voted that day "to advance [$705,000.000] to the design team for design services and expenses. Because under the MOU the construction company was to pay S&W, not the City, the construction company agreed to reimburse the City for the funds paid to S&W after the bond closing. The City paid S&W's invoice. S&W continued to work on the project, but in March 2004, the City abandoned its plans under the MOU and ended its relationship with S&W. S&W received no further compensation and sued the City for breach of contract under the MOU and the July 2003 agreement. The City argued there was no separate agreement and the payment of interim fees was merely an advance on fees under the MOU and furthermore, the MOU provided that S&W was to be paid by the construction company, not the City. The trial court granted partial summary judgment in favor of S&W, finding a contract existed between it and the City. On certiorari, the City conceded a contract exists, but argued the contract terms have been satisfied. The Supreme Court found the City's arguments were unpreserved and affirmed as modified. View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law

by
In approximately twenty years PCS Nitrogen, Inc. contributed to environmental contamination by manufacturing fertilizer and disturbing contaminated soil during various demolition activities. In 2003, Ashley II of Charleston, Inc. purchased 27.62 acres of the PCS's property. Since that time, Ashley II has incurred substantial costs in remediating the environmental contamination. In July 2008, Ashley II filed a complaint against PCS seeking a declaration of joint and several liability under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) due to costs of the environmental cleanup at the Site. Additionally, PCS asserted a third-party indemnification claim against the site's previous owner based on the indemnity provision in a 1966 purchase agreement, seeking indemnification for attorney's fees, costs, and litigation expenses incurred in establishing that the predecessor contributed to the contamination. The South Carolina Supreme Court anwered the following certified question from the United States District Court for the District of South Carolina: "Does the rule that a contract of indemnity will not be construed to indemnify the indemnitee against losses resulting from its own negligent acts, unless such intention is expressed in clear and unequivocal terms, apply when the indemnitee seeks contractual indemnification for costs and expenses resulting in part from its own strict liability acts? " In the context of the underlying claim in federal court, the South Carolina Court answered the question, "no." View "Ashley II v. PCS Nitrogen" on Justia Law

by
In 2006, DLI Properties, LLC (DLI), hired Allen Tate, a real estate brokerage firm, and Faile, Allen Tate's licensee, to serve as its agents in connection with the sale of certain real property in Lancaster, South Carolina. Petitioners, using Sharon Davis of Davis Integrity Realty, Inc. as their broker, offered to purchase the property. Petitioners sued Respondents alleging fraud, negligent misrepresentation, and violations of the South Carolina Unfair Trade Practices Act (the SCUTPA) based on DLI's acceptance of an offer on the property and Faile's representation that DLI would accept Petitioner's offer. Petitioners claimed Respondents made misrepresentations concerning the validity and effectiveness of their agreement to purchase the property. Petitioners asserted Respondents had a duty of care to communicate truthful information to Petitioners, and breached that duty by failing to disclose the ultimately successful offer, and the fact that DLI had not signed Petitioners' offer. Petitioners further alleged Respondents demonstrated a pattern of behavior sufficient to establish a SCUTPA violation. Petitioners appealed the circuit court's decision that granted summary judgment in favor of the Respondents. After careful consideration of the circumstances of the deal, the Supreme Court affirmed, noting that the appellate court erred only by not addressing the merits of Petitioners' appeal. On the merits, the Court affirmed the circuit court as modified. View "Woodson v. DLI Properties" on Justia Law

by
This case arose out of plaintiff Ferguson Fire's efforts to obtain payment for materials it supplied to defendant Preferred Fire Protection, LLC for defendant Immedion's data center. In 2007, Immedion, a telecommunications company, hired Rescom, L.L.C. to be the general contractor for improvements planned for its data center on property Immedion leased in Greenville. Rescom, in turn, hired Preferred Fire, a fire sprinkler company, as a subcontractor. In addition, Immedion directly hired Preferred Fire under a separate contract to install a special "pre-action" fire suppression system1 in its data center. To complete this work, Preferred Fire purchased materials from Ferguson Fire. Ferguson Fire began delivering materials to Preferred Fire in August, 2007, and the deliveries continued through October. In September, while its deliveries were in progress, Ferguson Fire sent a "Notice of Furnishing Labor and Materials" to Immedion advising it in relevant part that it had been employed by Preferred Fire to deliver labor, services, or materials with an estimated value of $15,000.00 to Immedion's premises. The Notice of Furnishing advised that it was being given as "a routine procedure to comply with certain state requirements that may exist," and that it was not a lien, nor any reflection on Preferred Fire's credit standing. Immedion paid Preferred approximately half of the contract price for installation of the system before receiving Ferguson Fire's Notice of Furnishing. After receiving the Notice, Immedion issued two additional checks to Preferred Fire for the unpaid balance of the contract price. Immedion paid everything it owed to Rescom, and it also paid its contractor Preferred Fire in full under the separate contract for the fire suppression system. However, Preferred Fire never paid Ferguson Fire for the materials it furnished. Ferguson brought a mechanic's lien foreclosure action against Immedion and Preferred Fire. Ferguson Fire contended (and the Supreme Court agreed) that the Court of Appeals erred in adding requirements to S.C Code Ann. 29-5-40 (2007) (governing a notice of furnishing) that were not in the statute itself and in concluding Ferguson Fire did not establish an effective lien upon which a foreclosure action could be premised. The Supreme Court reversed and remanded for further proceedings. View "Ferguson Fire v. Preferred Fire" on Justia Law

by
The Standard Fire Insurance Company appealed a court of appeals' decision that reversed the trial court's grant of summary judgment in its favor, and finding respondents Thomas, Debra, and Christopher were entitled to stack underinsured motorist (UIM) coverage despite an exclusion in Standard Fire's policy purporting to limit an insured's ability to stack such coverage when the vehicles insured under the subject policy were not involved in the accident. After review of the trial and appellate court records, the Supreme Court found no reversible error and affirmed the appellate court's decision. View "Carter v. Standard Fire Insurance" on Justia Law

by
Appellants Heritage Healthcare of Ridgeway, LLC, Uni-Health Post-Acute Care - Tanglewood, LLC (Tanglewood), and UHS-Pruitt Corporation (collectively, Appellants) ask this Court to reverse the circuit court's denial of their motion to compel arbitration in this wrongful death and survival action involving Appellants' allegedly negligent nursing home care. Tanglewood is a skilled nursing facility located in Ridgeway, owned and controlled by Appellants. In January 2007, Tanglewood and Respondent Darlene Dean entered into a nursing home residency agreement in which Tanglewood assumed responsibility for the care of Respondent's mother, Louise Porter (the patient). The same day, Respondent signed a separate, voluntary arbitration agreement. The patient did not sign either the residency agreement or the Agreement on her own behalf, although she was competent at the time of her admission to Tanglewood. Moreover, Respondent did not have a health care power of attorney empowering her to sign on the patient's behalf. In 2009, the patient fell three separate times within a ten day period, fracturing her hip in the third fall. Over the next two months, the patient underwent two hip surgeries; however, due to complications following the surgeries, the patient died on September 30, 2009. In late 2011, Respondent (acting in her capacity as personal representative of her mother's estate) filed a Notice of Intent (NOI) to file a medical malpractice suit against Appellants, as well as an expert affidavit in support of her NOI. Respondent also alleged claims for survival and wrongful death. In lieu of filing an answer to the complaint, Appellants filed a motion to dismiss pursuant to Rules 12(b)(1) and (6), SCRCP, or, in the alternative, a motion to compel arbitration and stay the litigation. Relying on "Grant v. Magnolia Manor-Greenwood, Inc.," (678 S.E.2d 435 (2009)), the circuit court invalidated the Agreement in its entirety and refused to compel arbitration between the parties. Appellants filed a motion to reconsider, which the circuit court denied. Upon review, the Supreme Court found that Respondent's argument that Appellants' waived their right to enforce the Agreement was without merit. On remand, the Supreme Court mandated that the circuit court consider her remaining arguments (concerning Respondent's authority to sign the Agreement and whether there was a meeting of the minds between the parties) prior to deciding whether to compel arbitration between the parties. View "Dean v. Heritage Healthcare" on Justia Law

by
Hard Hat Workforce Solutions, LLC (Hard Hat) appealed a circuit court order granting summary judgment in favor of Great American Insurance Company (GAI). Hard Hat argued it was entitled to make a claim against a payment bond GAI issued on a construction project. The threshold issue in this case was whether Hard Hat's bond claim must comply with section 29-5-440's "notice of furnishing" provision. The Supreme Court found it did not: three e-mails Hard Hat sent to a subcontractor, Walker White, created an issue of fact as to whether Hard Hat satisfied section 29-5-440's notice provisions. View "Hard Hat Workforce v. Mechanical HVAC" on Justia Law

by
Petitioner was injured in a car accident while riding as a passenger in a vehicle driven by a co-employee. The liability limits of the at-fault driver were tendered, and there was no underinsured motorist (UIM) coverage on the vehicle in which he was riding. Therefore, Petitioner submitted a claim for UIM benefits under a Progressive insurance policy, issued to Sarah Severn. At the time of the accident, Petitioner resided with Severn and their child. He described Severn as "his on again off again fiancé." Both Petitioner's and Severn's names appear on the Declarations Page of the Policy under the heading "Drivers and household residents." Under the heading "Additional information," Severn is listed as the "Named insured." Progressive denied UIM coverage to Petitioner under Part III of the Policy. According to the affidavit filed by Progressive's Claims Injury Operations Manager, "[t]he claim was denied because [Petitioner] did not fall within the terms, provisions and conditions of [the Policy] to qualify for benefits under the [UIM] provisions," as Petitioner "was only listed as a 'driver' on the policy and not a named insured, nor was he a resident relative of the named insured." The Supreme Court granted Bell's petition for review of the court of appeals' decision affirming the circuit court's grant of summary judgment in favor of Progressive Direct Insurance Company. Finding no reversible error, the Supreme Court affirmed. View "Bell v. Progressive Direct Insurance" on Justia Law

by
The issue this case presented to the Supreme Court started from an agreement between Respondents, the University of South Carolina and the University Gamecock Club, and Appellant George M. Lee, III. In exchange for Appellant purchasing a $100,000 life insurance policy and naming the University the sole, irrevocable beneficiary of the policy, Appellant was given the "opportunity to purchase tickets" for his lifetime to University football and basketball games. Years later, the University instituted a program that required all Gamecock Club members, including Appellant, to pay a seat license fee as a prerequisite for purchasing season tickets. Believing that the University could not require him to pay additional consideration for the opportunity to purchase tickets without violating the agreement, Appellant brought a declaratory judgment action. The trial court entered judgment for the University and the Gamecock Club, finding that Appellant was not deprived of the opportunity to purchase season tickets when the University instituted the seat license fees. The Supreme Court reversed: the Agreement unambiguously prohibited the University from requiring Lee to pay the seat license fee as a prerequisite for the opportunity to purchase tickets pursuant to the Agreement. View "Lee v. University of South Carolina" on Justia Law